This photo shows the layout of the boiler backhead

This was the first formal inspection of our new boiler while in steam. The inspector required an hydraulic pressure test before the steam examination which would check the boiler complete with all the fittings.
At 240 psi water test pressure there were several leaks, most were cured by a bit of adjustment. The three remaining minor water drips were noted in the log for future attention.